o 1 day off (2/10)
== Progress ==
o Linaro GCC (6/10)
* FSF branch merge into linaro GCC 5 branch
* Troubleshot various regression after the merge
* Delivered GCC 5.2 2015.11 snapshot
o Upstream work (1/10)
* Sanitizing gfortran testsuite
o Misc (1/10)
* Various meetings
== Plan ==
o Continue on sanitizing testsuite
o Backports, infra, ...
== Progress ==
o Linaro GCC (6/10)
* FSF branch merge into linaro GCC 5 branch
* Troubleshot various regression after the merge
* Delivered GCC 5.2 2015.11 snapshot
o Upstream work (1/10)
* Sanitizing gfortran testsuite
o Misc (1/10)
* Various meetings
== Plan ==
o Continue on sanitizing testsuite
o Backports, infra, ...