Discussion:
[ACTIVITY] Week 26
Yvan Roux
2016-07-04 07:59:09 UTC
Permalink
o One day off (2/10)

== Progress ==
o Extended Validation (3/10)
- Benchmarking job babysitting.
- Looked at Dejagnu issue (pid killing, resurrected an old patch)

o Upstream GCC (3/10)
- __sync bultin fix for ARMv8.1:
Careful read of the doc shows that there is no issue with the
current implementation (no need to add an extra DMB, acq/rel
semantic is sufficient in this case)
- AArch64 and ARM backend cleanup w/r to reload remaining hooks
Analysis and validation on-going

o Misc (2/10)
* Various meetings and discussions.

== Plan ==
o Continue on-going tasks